Paving · per SY · FW item 3211.0501

6" Lime Treatment

11 observations from Dallas–Fort Worth public works, Mar 4, 2025 – Apr 10, 2025.

Median
$4.50
per SY
Typical range (p25–p75)
$4.00–$10.00
middle half of observations
Full range
$3.90–$50.00
low to high
Observations
11
accepted line items
Median unit price by quarter (per SY)
$3.87 $4.55 $5.22 2025-Q12025-Q2 $5.09 $4.00

Quarter of the approval date on the source document. Quarters with no observation are not plotted.

Median by segment (per SY)
Developer (CFA)
$4.50
11 obs
City contract
not covered in DFW Beta
0 obs
TxDOT
not covered in DFW Beta
0 obs

Bar is the median; the outlined span is the p25–p75 range. TxDOT is not part of DFW Beta coverage yet.

Observations

Every row links to the page of the public document it was read from. The description column shows the text exactly as printed in that document.

Date Unit price Quantity Segment Document Party As printed Receipt
Apr 10, 2025 $6.00 2,418 SY Developer (CFA) Final pay · CSC 061327 Ashton Dallas Residential LLC 6" LIME TREATMENT p.5 ↗
Apr 10, 2025 $4.00 12,370 SY Developer (CFA) Final pay · CSC 061327 Ashton Dallas Residential LLC 6" LIME TREATMENT p.5 ↗
Apr 7, 2025 $4.00 16,817 SY Developer (CFA) Final pay · CSC 061036 Conatser Construction 6" LIME TREATMENT p.4 ↗
Mar 27, 2025 $4.00 11,030 SY Developer (CFA) Final pay · CSC 061172 Conatser Construction 6" LIME TREATMENT p.4 ↗
Mar 26, 2025 $14.00 683 SY Developer (CFA) Final pay · CSC 057853 The Ridgemont Company 6" LIME TREATMENT ( CO 3) p.4 ↗
Mar 24, 2025 $50.00 294 SY Developer (CFA) Final pay · CSC 050202 San Saba Construction 6" LIME TREATMENT p.4 ↗
Mar 24, 2025 $50.00 294 SY Developer (CFA) Final pay · CSC 050201 San Saba 6" LIME TREATMENT p.4 ↗
Mar 24, 2025 $4.00 31,008 SY Developer (CFA) Final pay · CSC 060711 Conatser Construction, TX L.P. 6" LIME TREATMENT ( CO# 1) p.4 ↗
Mar 20, 2025 $3.90 36,748 SY Developer (CFA) Final pay · CSC 060374 Glenn Thurman, Inc. 6" LIME TREATMENT p.4 ↗
Mar 17, 2025 $5.68 7,965 SY Developer (CFA) Award · CSC 062976 Forestar ((USA) Real Estate Group, Inc. 6" Lime Treatment p.23 ↗
Mar 4, 2025 $4.50 3,427 SY Developer (CFA) Final pay · CSC 061438 NewPad Building Company, LLC 6" LIME TREATMENT p.4 ↗

Source: fortworth_laserfiche. Every row passed the quality gate — quantity × unit price reconciles with the extended value printed on the document. How the data works →