Traffic Control

17 observations from Dallas–Fort Worth public works, Oct 17, 2023 – Apr 14, 2025.

Median
$4,500
per MO
Typical range (p25–p75)
$2,500–$6,500
middle half of observations
Full range
$450–$12,000
low to high
Observations
17
accepted line items
Median unit price by quarter (per MO)
$2,460 $5,250 $8,040 2023-Q42025-Q12025-Q2 $7,500 $3,000

Quarter of the approval date on the source document. Quarters with no observation are not plotted.

Median by segment (per MO)
Developer (CFA)
$5,500
16 obs
City contract
$4,000
1 obs
TxDOT
not covered in DFW Beta
0 obs

Bar is the median; the outlined span is the p25–p75 range. TxDOT is not part of DFW Beta coverage yet.

Observations

Every row links to the page of the public document it was read from. The description column shows the text exactly as printed in that document.

Date Unit price Quantity Segment Document Party As printed Receipt
Apr 14, 2025 $4,500.00 1 MO Developer (CFA) Final pay · CSC 060289 KDP Stockyards, lLC TRAFFIC CONTROL p.5 ↗
Apr 10, 2025 $6,500.00 1 MO Developer (CFA) Final pay · CSC 061327 Ashton Dallas Residential LLC TRAFFIC CONTROL p.5 ↗
Apr 10, 2025 $3,500.00 1 MO Developer (CFA) Final pay · CSC 061327 Ashton Dallas Residential LLC TRAFFIC CONTROL p.5 ↗
Apr 10, 2025 $2,500.00 1 MO Developer (CFA) Final pay · CSC 061327 Ashton Dallas Residential LLC TRAFFIC CONTROL p.4 ↗
Apr 10, 2025 $2,500.00 1 MO Developer (CFA) Final pay · CSC 061327 Ashton Dallas Residential LLC TRAFFIC CONTROL p.6 ↗
Apr 7, 2025 $2,500.00 1 MO Developer (CFA) Final pay · CSC 061036 Conatser Construction TRAFFIC CONTROL p.4 ↗
Mar 27, 2025 $6,500.00 2 MO Developer (CFA) Final pay · CSC 061172 Conatser Construction TRAFFIC CONTROL p.5 ↗
Mar 26, 2025 $12,000.00 12 MO Developer (CFA) Final pay · CSC 057853 The Ridgemont Company TRAFFIC CONTROL p.5 ↗
Mar 24, 2025 $6,500.00 1 MO Developer (CFA) Final pay · CSC 050202 San Saba Construction TRAFFIC CONTROL p.4 ↗
Mar 24, 2025 $6,500.00 1 MO Developer (CFA) Final pay · CSC 050201 San Saba TRAFFIC CONTROL p.4 ↗
Mar 20, 2025 $2,000.00 1 MO Developer (CFA) Final pay · CSC 060374 Glenn Thurman, Inc. TRAFFIC CONTROL p.4 ↗
Mar 18, 2025 $800.00 1 MO Developer (CFA) Final pay · CSC 062423 R&D Burns Bros. Inc. TRAFFIC CONTROL p.4 ↗
Mar 17, 2025 $7,500.00 1 MO Developer (CFA) Award · CSC 062973 Muse Capital LLC Traffic Control p.24 ↗
Mar 11, 2025 $4,000.00 2 MO City contract Change order · CSC 061454 Woody Contractors, Inc. TRAFFIC CONTROL p.2 ↗
Mar 4, 2025 $6,500.00 1 MO Developer (CFA) Award · CSC 062908 FW Club LP Traffic Control p.19 ↗
Mar 4, 2025 $450.00 2 MO Developer (CFA) Final pay · CSC 061438 NewPad Building Company, LLC TRAFFIC CONTROL p.4 ↗
Oct 17, 2023 $7,500.00 1 MO Developer (CFA) Award · CSC 060289 KDP Stockyards, lLC Traffic Control p.24 ↗

Source: fortworth_laserfiche. Every row passed the quality gate — quantity × unit price reconciles with the extended value printed on the document. How the data works →